6 BioCNG plants and more than 11,100 small biogas plants commissioned under National Bioenergy Programme – EQ Mag
0
0
The Union Minister for New & Renewable Energy and Power has informed that the Ministry of New and Renewable Energy notified the National Bioenergy Programme (NBP) in November, 2022 for the period 01.04.2021 to 31.03.2026. This programme, with a budgetary outlay of Rs. 1715 Crore, shall be implemented in two phases. The first phase has a budgetary outlay of Rs. 858 Crore. This programme provides Central Financial Assistance (CFA) for setting up of Bioenergy plants.
As on 31.07.2023, six BioCNG plants and 11,143 small biogas plants have been commissioned, sanctions for which have been issued under the NBP guidelines notified on 02.11.2022. The State/ UT-wise details of these plants are given below.
S. No. | State / Union Territory | No. of plants commissioned and sanctions for which have been issued under the NBP guidelines notified on 2.11.2022 | |
No. of Small Biogas Plants | No. of BioCNG plants | ||
1 | Andhra Pradesh | 30 | 0 |
2 | Bihar | 9 | 0 |
3 | Chhattisgarh | 118 | 0 |
4 | Goa | 11 | 0 |
5 | Gujarat | 224 | 0 |
6 | Haryana | 43 | 0 |
7 | Karnataka | 2488 | 0 |
8 | Kerala | 683 | 0 |
9 | Madhya Pradesh | 2083 | 0 |
10 | Maharashtra | 4167 | 3 |
11 | Odisha | 96 | 0 |
12 | Punjab | 835 | 1 |
13 | Rajasthan | 20 | 0 |
14 | Tamil Nadu | 46 | 1 |
15 | Uttar Pradesh | 126 | 1 |
16 | Uttarakhand | 164 | 0 |
Total | 11143 | 6 |
National Bioenergy Programme, inter alia, promotes the utilization of biomass such as surplus agricultural residue, agro-based industrial residue, industrial wood-waste, forest residue, energy plantation based biomass etc. for energy generation and therefore would not pose a risk of deforestation.
This information has been given by the Union Minister for New & Renewable Energy and Power Shri R. K. Singh, in a written reply to a question, in Lok Sabha on August 10, 2023.
Related posts:
- Record of discussion of meeting on development of Ultra Mega Renewable Energy Power Parks (UMRPPs) under the existing Solar Park Scheme – reg.
- Wind Turbine Models included in the RLMM after declaration of new procedure (i.e 01 November 2018)
- Take Corrective Measures: Par Panel to MNRE on Missing Annual Renewable Targets
- Updation of List (Manufacturers and Models of Solar PV Modules) of ALMM Order,2019-REG