CLARIFICATIONS TO AMENDMENT-I : SELECTION OF SOLAR POWER DEVELOPERS FOR SETTING UP OF 150MW (50MW X 3) GRID CONNECTED FLOATING SOLAR POWER PROJECTS TO BE INSTALLED AT RIHAND DAM, UP
This has reference to the RfS No. SECI/C&P/SPD/RfS/150MW FLOATING/UP/R1/092018 dated 06.09.2018 regarding “Selection of Solar Power Developers for Setting up of 150MW (50MW x 3) Grid Connected Floating Solar Power Projects to be installed at Rihand Dam (also known as Govind Ballabh Pant Sagar Reservoir), Sonbhadra District, Uttar Pradesh”.
The pre-bid meeting for the subject tender has been organized on 14.09.2018 @ 15:00 HRS (IST) at SECI, New Delhi Office. The Amendment-I to RfS document including draft PPA and PSA have been uploaded on www.tcil-india-electronictender.com (Only viewed on Microsoft Internet explorer 10.x or above browser) on 09.10.2018 and 12.10.2018.
Some of the prospective bidders have raised query regarding ambiguity in Sr. No. 03 of Amendment-I. Hence a clarification document is being attached. Prospective bidders are requested to refer the attachment for details.
Prospective bidders are requested to remain updated for any notices/ amendments/ clarifications etc. to the RfS documents through the websites www.seci.co.in and https://www.tcil-india-electronictender.com as no separate notification will be issued.
Tender Search Code (TSC) for the RfS in TCIL : SECI-2018-TN000013
Tender ID (TSC) for the RfS in CPPP : 2018_SECI_315931_1
Clarifications to Amendment-I
Source: seci.co.in
Related posts:
- SUBMISSION OF QUERIES : SELECTION OF SOLAR POWER DEVELOPERS FOR SETTING UP OF 150MW (50MW X 3) GRID CONNECTED FLOATING SOLAR POWER PROJECTS TO BE INSTALLED AT RIHAND DAM, UP
- EXTENSION OF BID SUBMISSION DEADLINE-VII : SELECTION OF SOLAR POWER DEVELOPERS FOR SETTING UP OF 150MW (50MW X 3) GRID CONNECTED FLOATING SOLAR POWER PROJECTS TO BE INSTALLED AT RIHAND DAM, UP
- UP govt clears state’s first floating solar power plant on Rihand Dam
- NSEFI Representation to UP govt on uncertainty prevailing the UP