In the Matter of: Petition for payment against the Units Injected by 05 MW Solar Power Plant and Refund of Transmission Charges under protest
0
0
In the Matter of: Petition for payment against the Units Injected by 05 MW Solar Power Plant from 21st Jun 2018 to 30th Apr 2019 and Refund of Transmission Charges under protest.
For more information please see below link:
Related posts:
- HERC Seeks approval of Commission for procurement of 250 MW solar power on long term basis
- IN THE MATTER OF: Application for approval of Source and adoption of tariff by the Hon’ble Commission for quantum of 1 MW solar power
- HERC: Application for approval of source and adoption of tariff by the Commission for quantum of 240 MW, floated for procurement of 300 MW solar power on long term basis through tariff based competitive bidding proces