1. Home
  2. Featured
  3. SECI 1200 MW Solar PV Project (ISTS-VIII)
SECI 1200 MW Solar PV Project (ISTS-VIII)

SECI 1200 MW Solar PV Project (ISTS-VIII)

0
0

 

SECI 1200 MW Solar PV Project (ISTS-VIII)

1. Bid submission: 04/02/2020
2. Pre-Bid Meeting: 15/01/2020
3. Ceiling Tariff: 2.78/kWh
4. EMD: 4 Lakh / MW
5. PPA : 90 Day + LOA
6. FC: 12 Months + PPA
7. Commissioning: 18 months + PPA

 

RFS FOR 1200 MW ISTS-CONNECTED SOLAR PV POWER PROJECTS IN INDIA (ISTS-VIII)


RfS for setting up of 1200 MW ISTS-connected Solar PV Power Projects in India has been uploaded on the website, https://www.bharat-electronictender.com.

Pre-bid meeting is scheduled on 15.01.2020 (1430 hrs), in the office of SECI

Last date of bid submission: 04.02.2020 (1800 hrs)

Tender document

tags:
Anand Gupta Editor - EQ Int'l Media Network

LEAVE YOUR COMMENT

Your email address will not be published. Required fields are marked *