1. Home
  2. India
  3. Suzlon bags order for 39-MW wind energy project from Thermax Group firm First Energy – EQ Mag
Suzlon bags order for 39-MW wind energy project from Thermax Group firm First Energy – EQ Mag

Suzlon bags order for 39-MW wind energy project from Thermax Group firm First Energy – EQ Mag

0
0

Renewable energy solution provider Suzlon on Thursday announced that it has bagged a 39-MW wind power project from Thermax Group company First Energy

This order is part of a 100-MW wind-solar hybrid project by First Energy 5 Pvt Ltd, a company statement said.

Suzlon will install 13 wind turbine generators (WTGs) with a hybrid lattice tubular (HLT) tower and a rated capacity of 3 MW each.

The project, to be located at Thalaikattupuram, Tuticorin in Tamil Nadu, is expected to be commissioned in 2024.

As part of the agreement, Suzlon will supply the wind turbines (equipment supply) and supervise the project including erection and commissioning.

Suzlon will also provide comprehensive operations and maintenance services post-commissioning.

J P Chalasani, CEO, Suzlon Group, said in the statement, “This is our first order with the (Thermax) group and features our 3 MW series product, which is one of the largest wind turbines in India today.”

Ravi Damaraju, Director, First Energy, said, “As a leading renewable energy solutions provider with proven technology, Suzlon is the right partner for us for this project.

Source: PTI
Anand Gupta Editor - EQ Int'l Media Network