BTN Solar to issue appropriate direction to the respondent complete construction of requisite infrastructure beyond the Delivery Point required for evacuation of the entire contracted capacity of 100 MWs
M/s. BTN Solar Private Limited/ To issue appropriate direction to the respondent complete construction / commissioning of requisite infrastructure beyond the Delivery Point required for evacuation of the entire contracted capacity of 100 MWs
TNERC refused to extend the commissioning deadline of 50 MW solar power project
Conclusion:-
We conclude by observing that only 50 MW capacity can be allowed to be declared commissioned as per the PPA and a capacity to the extent of remaining 50 MW gets terminated for the reasons stated in para 17 and the PPA shall stand amended to the capacity of 50 MW only as per the clause 14 of the PPA. However, it is open to the parties to renegotiate with respect to the applicable tariff for the remaining 50 MW and enter a new PPA with appropriate regulatory approval of the Commission.
For more information please see below link:
Related posts:
- Order – Grant connectivity and net metering to the petitioner for the implementation of 4 MWp Roof Top Solar Project for Southern Railway
- Power procurement by Distribution Licensee from Bagasse based Co-generation plants
- TNERC Rejects VSR Solar Power Petition for Extending Project Commissioning Deadline
- Petition for implementation of the KUSUM (Component C) – Comments invited