Petition under Section 79 of the Electricity Act, 2003 seeking declaration that the Transmission Agreement for Connectivity dated 7.8.2018, Transmission Service Agreement dated 6.9.2018 and Agreement for Long Term Access dated 6.9.2018 executed between ReNew Wind Energy (TN) Pvt. Ltd. and Power Grid Corporation of India Limited stand frustrated on account of Force Majeure Even and impossibility of performance along with directions to restrain Power Grid Corporation of India Limited from invoking bank guarantees and levying relinquishment charges.
For more information please see below link:
Related posts:
- In the matter of: Petition for adoption of tariff for the Scheme for setting up of 1000 MW Inter-State Transmission System (ISTS) connected Wind Power
- CERC Adopted Individual Tariff for 3 GW of the Power Projects
- Petition Regarding Bank Guarantee of 300 MW Wind Project