Construction of 60MW solar power plant in Khargone likely to be completed by year-end – EQ
0
0
In Short : The construction of a 60 MW solar power plant in Khargone, Madhya Pradesh, is expected to be completed by the end of the year. This project will enhance the region’s renewable energy capacity and contribute to India’s clean energy goals. Once operational, the plant will supply solar power to the grid, supporting the country’s ongoing efforts to increase sustainable energy production.
In Detail : INDORE : The construction of a 60 megawatt solar power plant in Khargone in Madhya Pradesh at an estimated cost of Rs 308 crore is likely to be completed by the end of the year, an Indore Municipal Corporation official said on Thursday.
The foundation stone of the plant, which is coming up on an area of 220 acres in Jalud village in the neighbouring district, was laid via video conference by Prime Minister Narendra Modi on December 25 last year.
“Of the estimated cost of Rs 308 crore, a sum of Rs 244 crore was raised by the Indore civic body through green bonds that were issued to the public in February last year,” the official said.
Related posts:
- 525 KW solar power plant set up in Golden Temple – EQ Mag Pro
- Cochin Airport to commission 12 MWp solar power plant at Payyanur – EQ Mag Pro
- SPIC’s captive floating solar power plant in TN goes on stream, CM inaugurates unit – EQ Mag Pro
- TANCEM to set up 10 MW solar power plant for captive use – EQ Mag Pro