  3. DVC’s Rs 1,500 crore push to modernise power supply – EQ
DVC’s Rs 1,500 crore push to modernise power supply – EQ

DVC’s Rs 1,500 crore push to modernise power supply – EQ

0
0

In Short : The Damodar Valley Corporation (DVC) has initiated a Rs 1,500 crore project to modernize its power supply infrastructure and cut transmission and distribution losses. The plan includes upgrading aging systems, deploying smart grid technologies, and enhancing energy management. Aimed at improving efficiency and reliability, the project supports India’s goals for a sustainable power sector while boosting regional economic growth and reducing energy wastage.

In Detail : Kolkata -Damodar Valley Corporation (DVC) has launched a Rs 1,500 crore project to modernise power supply in its command area to ensure round-the-clock quality power and to reduce aggregate technical and commercial (AT&C) losses, an official said on Sunday.

DVC’s entire distribution network primarily serves industries, with negligible supply to retail consumers.

The project focuses on shifting from conventional power distribution to a state-of-the-art, technology-driven system to establish a robust primary and secondary distribution network across DVC’s command area spanning 24,235 square kilometres in West Bengal and Jharkhand.

“The project capex is nearly Rs 1,500 crore and will be completed in 18 months. The system integrates advanced features such as a distribution management system, outage management system, customer relation management, metering data management system, GIS mapping for real-time communication, ring main units (RMU), and fiber optic-based metering communication systems,” DVC member (Finance) Arup Sarkar told PTI.

The new distribution system incorporates cutting-edge technologies, including unmanned container-based substations (E-houses) equipped with GIS-based 33 KV panels, modular battery chargers, and substation automation systems (SAS), he said.

In the first phase, DVC will deploy 12 E-houses, 8 conventional indoor-based 33/11 KV substations, and 4 GIS-based prefab substations. The first E-house was commissioned on January 3, 2025, in Dhanbad, with additional E-houses in BIADA, Deoli, Giridih, Hazaribagh, and Sindri slated for commissioning by March 2025, Sarkar said.

The entire distribution network, including consumer feeders, will be managed through two advanced control centres located in Kalyaneshwari, West Bengal, and Koderama, Jharkhand, DVC said.

These centres will ensure hot redundancy and feature a 24X7 customer cell. The new system will enable automatic consumer connection and disconnection based on billing and collection, allowing customers to manage their services seamlessly through a mobile app, eliminating the need for physical interaction, the official said.

“This technological leap marks a significant milestone in DVC’s journey towards modernising power distribution. By leveraging cutting-edge solutions, we aim to enhance operational efficiency, reduce losses, and provide our consumers with a seamless and transparent experience,” Sarkar said.

DVC has partnered with industry leaders such as Tata Consulting Engineers, Siemens Columbia, Siemens India, Transafe, and Techno Electric to drive power distribution sector reforms for enhanced reliability, efficiency, and customer satisfaction.

Anand Gupta Editor - EQ Int'l Media Network