Order dated 13/08/20 for Petition Number 1583 of 2020 – Eden renewable Jasmin Ltd vs UPPCL – Petition under Section 86(1)(b) of the Electricity Act, 2003 read with Section 63 of the Electricity Act, 2003 and Regulation 57 of the Uttar Pradesh Electricity Regulatory Commission (Conduct of Business) Regulations, 2019 seeking extension of time-period for Scheduled Commissioning Date under the Power Purchase Agreement dated 21.12.2018 entered into between the Petitioner and UPPCL in Petition no 1583/2020

For more information please see below link: