Petition filed by MP Power Management Co in connection with the disputes and differences arising due to breach of PPA
0
0
Petition filed by Madhya Pradesh Power Management Company Limited under Sections 79(1)(c), (f), (k) and other applicable provisions of the Electricity Act, 2003 in connection with the disputes and differences arising due to breach of Power Purchase Agreement dated 8.8.2005 entered between it and Nuclear Power Corporation of India Limited and allowing the claim for damages. Madhya Pradesh Power Management Company Limited
For more information please see below link:
Related posts:
- In the matter of: Seeking compensation on account of „Change in Law events‟ under Article 10 of the Power Purchase Agreement entered into between the Petitioner and the Respondents
- In the matter of: Approval under regulation-86 of CERC (Conduct of Business) and CERC (Terms and Conditions of Tariff) for determination of Transmission Tariff
- Application for Adoption of Transmission Charges