1. Home
  2. Policy & Regulation
  3. Petition for removal of difficulty in obtaining net metering facility at a connectivity level of 132 KV
Petition for removal of difficulty in obtaining net metering facility at a connectivity level of 132 KV

Petition for removal of difficulty in obtaining net metering facility at a connectivity level of 132 KV

0
0

 

Petition purported to be filed Under Regulation A18 of JSERC (Rooftop Solar PV Grid Interactive Systems and Net/Gross Metering) Regulations, 2015 for removal of difficulty in obtaining net metering facility at a connectivity level of 132 KV.

We allow net metering connectivity of the petitioner for Solar power plant of 1998.8kW at 132 KV voltage supply subject to fulfilment of
requirements with regard to system protection, data communication and metering of JUSNL, SLDC and JBVNL respectively as well as complying standard norms of CEA

For more information please see below link:

Anand Gupta Editor - EQ Int'l Media Network