Petition seeking compensation on account of Change in Law
0
0
Petition seeking compensation on account of Change in Law under Section 79 of the Electricity Act, 2003 read with statutory framework governing procurement of power through competitive bidding and Article 10 of the Power Purchase Agreement dated 1.4.2013 entered into between Thermal Powertech Corporation India Ltd. and the Distribution Companies in the States of Andhra Pradesh and Telangana.
For more information please see below link:
Related posts:
- In the matter of: Petition for directions to make Energy Charges as pass through based on the actual fuel cost incurred by the Petitioner
- In the matter of: Approval of transmission tariff of Asset-I
- Seeking relinquishment of Long-term Access of 386 MW in Western Region