1. Home
  2. Featured
  3. Power Projects with 11,703 MW electricity generation capacity have been commissioned in the North Eastern Region: Union Power and New & Renewable Energy Minister – EQ
Power Projects with 11,703 MW electricity generation capacity have been commissioned in the North Eastern Region: Union Power and New & Renewable Energy Minister – EQ

Power Projects with 11,703 MW electricity generation capacity have been commissioned in the North Eastern Region: Union Power and New & Renewable Energy Minister – EQ

0
0

In Short : The statement highlights that power projects with a total electricity generation capacity of 11,703 megawatts (MW) have been commissioned in the North Eastern Region of India. This indicates significant efforts to enhance the energy infrastructure in the region, addressing power generation and distribution needs. The development aligns with the broader goal of ensuring access to reliable and sustainable energy sources for the residents of the North Eastern Region.

In Detail : The Union Minister for Power and New & Renewable Energy has informed that the States in the North Eastern part of our country are endowed with large Hydro potential and that the government has taken the following initiatives in order to attract investments in developing Hydro Power in the region.

Declaring Large Hydro Power (LHPs) (> 25 MW projects) as renewable energy source.
Putting in place a Hydro Purchase Obligation (HPO)
Tariff rationalization measures for bringing down hydro power tariff.
Budgetary support for flood moderation/storage in Hydro Electric Projects (HEPs).
Budgetary support towards cost of enabling infrastructure, i.e. roads/bridges.
Full 100 % waiver of Inter State Transmission System (ISTS) charges for new hydro power projects in which construction work is awarded and Power Purchase Agreement (PPA) is signed on or before 30.06.2025.

The details of waiver of ISTS charges trajectory where construction work is awarded and PPA is signed after 30.06.2025 are given below.

Sl. No Awarded of Construction work + Signing of PPA Waiver of ISTS charges
1 01.07.2025 to 30.06.2026 75%
2 01.07.2026 to 30.06.2027 50%
3 01.07.2027 to 30.06.2028 25%

Details of waiver ISTS charges trajectory where construction work is awarded and PPA is signed after 30.06.2025

State Name of Project Fuel Capacity (MW)
Arunachal Pradesh Kameng HPS Hydro 600
Pare Hydro 110
Ranganadi HPS Hydro 405
Assam Karbi langpi HPS Hydro 100
Lakwa GT Gas 97
Lakwa Replacement Power Project Gas 70
Namrup CCPP Gas 139
Kathalguri CCPP Gas 291
Khondong HPS Hydro 50
Kopili HPS Hydro 200
Bongaigaon TPP Coal 750
Manipur Leimakhong DG Diesel 36
Loktak HPS Hydro 105
Meghalaya Kyrdemkulai HPS Hydro 60
Myntdu (leshka) ST-1 HPS Hydro 126
New Umtru HPS Hydro 40
Umiam HPS ST-I Hydro 36
Umiam HPS ST-IV Hydro 60
Mizoram Tuirial HPS Hydro 60
Nagaland Doyang HPS Hydro 75
Tripura Agartala GT Gas 135
Monarchak CCPP Gas 101
Tripura CCPP Gas 727
Baramura GT Gas 42
Rokhia GT Gas 63
Sikkim Rangit HPS Hydro 60
Teesta V HPS Hydro 510
Teesta-III HPS Hydro 1,200
Tashiding HPS Hydro 97
Rongnichu HPS Hydro 113
Chuzachen HPS Hydro 110
Jorethang Loop Hydro 96
Dikchu HPS Hydro 96

Projects with aggregate installed capacity of 11,703MW (6,760 MW from conventional sources of energy and 4,943 MW from non-conventional sources of energy) have been commissioned in the North Eastern region. The details are given below.

Details of commissioned power projects (from conventional sources of energy) located in North Eastern region (as on 31.10.2023)

HPS – Hydro Power Station, GT – Gas Turbine, CCPP- Combined Cycle Power Plants, ST – Steam Turbine

State-wise installed capacity of non-conventional sources of energy as on 30.11.2023 in

North Eastern Region

(In MW)

STATES Small Hydro Power Bio Power Solar Power Large Hydro Power Total Capacity
1 Arunachal Pradesh 133 12 1,115 1,260
2 Assam 34 2 156 350 542
3 Manipur 5 13 105 123
4 Meghalaya 55 14 4 322 395
5 Mizoram 45 30 60 136
6 Nagaland 33 3 75 111
7 Sikkim 55 5 2,282 2,342
8 Tripura 16 18 34

Currently, eight hydroelectric projects with aggregate installed capacity of 6,037 MW are under construction in the North Eastern region of the country. The details are given below.

List of Hydro Electric Projects (above 25 MW) under construction in North Eastern Region

Further, Central Electricity Authority (CEA) has accorded concurrence to seventeen hydroelectric schemes (aggregating to 14,589 MW) in North Eastern region. The details are given below.

This information has been given by the Union Minister for Power and New & Renewable Energy Shri R. K. Singh, in a written reply to a question, in Rajya Sabha today, December 12, 2023.

Anand Gupta Editor - EQ Int'l Media Network