1. Home
  2. Featured
  3. Pre-bid meeting: RfS for setting up of 125 MW/ 500 MWh Standalone BESS in Kerala with VGF (ESS-3) – EQ
Pre-bid meeting: RfS for setting up of 125 MW/ 500 MWh Standalone BESS in Kerala with VGF (ESS-3) – EQ

Pre-bid meeting: RfS for setting up of 125 MW/ 500 MWh Standalone BESS in Kerala with VGF (ESS-3) – EQ

0
0

With reference to the RfS for the Selection of Battery Energy Storage System Developers for Setting up 125 MW/ 500 MWh of Battery Energy Storage System in Kerala with VGF for “on Demand” usage under Tariff-based Competitive Bidding (ESS-3), the Substation site visit and pre-bid meeting are scheduled as per following details:

Location of Substation Site Visit and Pre-bid Meeting: https://maps.app.goo.gl/DECTeWW91QdgrP6M8

Date of Substation Site Visit: 09.01.2025

Contact Details for Substation Site Visit: Ranjith Lal (9496011377) [Assistant Executive Engineer (Mylatti s/s)]

Name of the Substation and Pre-bid meeting Venue: 220 kV Substation Mylatti, Kerala- 671 318

Date and time of Pre-bid meeting: 10.01.2024 (11:00 AM IST)

Mode of Pre-bid meeting: Offline Mode Only

Prospective bidders interested in visiting the Substation Site and participating in the pre-bid meeting are required to register themselves by mailing their names and organization details to biblesh@seci.co.in (Sh. Biblesh Meena, Manager, SECI, +91-7827683435).

Anand Gupta Editor - EQ Int'l Media Network