To uphold the obligation of the State Distribution licensee in terms of PPAs

TANGEDCO/To uphold the obligation of the State Distribution licensee in terms of power purchase agreements has been and continues to be stranded and there is an unavoidable obligation and incidence to bear fixed costs consequent to such agreements etc.,. For more information please see below link.

Petitions in the matter of Filing of Tariff Approval of and Determination for FY 2024-25 – EQ

TANGEDCO is directed to verify the claim made by the petitioner & settle within 30 days with interest at 12% P.A.

TANGEDCO is directed to verify the claim made by the petitioner and after deducting the amount already paid, settle the same within 30 days from the date of this order together with interest at 12% per annum from the date of filing of this petition till realisation. In the circumstances, there will be no order […]

Petitions in the matter of Filing of Tariff Approval of and Determination for FY 2024-25 – EQ

TANGEDCO – To uphold the obligation of the State Distribution licensee in terms of power purchase agreements

TANGEDCO/To uphold the obligation of the State Distribution licensee in terms of power purchase agreements has been and continues to be stranded and there is an unavoidable obligation and incidence to bear fixed costs consequent to such agreements etc.,. For more information please see below link.

Petitions in the matter of Filing of Tariff Approval of and Determination for FY 2024-25 – EQ

TNEB Floats Tender For 1 MW Solar PV Power Plant with 1MW /3.0 MWH BESS in Tamilnadu

TNEB Floats Tender For 1 MW Solar PV Power Plant with 1MW /3.0 MWH BESS in Tamilnadu TENDER FOR DESIGN, ENGINEERING, SUPPLY, CONSTRUCTION, ERECTION, TESTING, COMMISSIONING OF 1 MW (AC) SOLAR PV POWER PLANT WITH 1MW /3.0 MWH BESS INCLUDING 10 YEARS PLANT O and M IN TAMILNADU The last date to submit the bids […]

SECI issue Tender for 1000 MW ISTS-Connected Solar PV Power Projects in India – EQ

TANGEDCO – Consultancy Services for CGP verification for Wind/Solar Energy Generators in Coimbatore

TANGEDCO – Consultancy Services for CGP verification for FY 2014-15 to 2019- 2020 Wind/Solar Energy Generators in Coimbatore Region having multiple captive users (Other than top 30 generators) The last date to submit the bids is March 3, 2021 For more information please see below link:

SECI issue Tender for 1000 MW ISTS-Connected Solar PV Power Projects in India – EQ

TNERC Rejects VSR Solar Power Petition for Extending Project Commissioning Deadline 

TNERC Rejects VSR Solar Power Petition for Extending Project Commissioning Deadline M/s VSR Solar Power Private Limited / Grant the Petitioner a project specific extension of the COD by eighteen months i.e. 21.3.2019 to 21.9.2020 in respect of the Petitioner’s SPG under PPA etc For more information please see below link:

Petitions in the matter of Filing of Tariff Approval of and Determination for FY 2024-25 – EQ

APTEL Says Banking Energy for Wind Power Projects Will Continue

APTEL Says Banking Energy for Wind Power Projects Will Continue For more information please see below link: For the foregoing reasons, we find the impugned order, to the extent challenged, to be suffering from the vices of being shorn of reasons, arbitrary, capricious, unjust and inequitable. We, therefore, set aside and vacate the directions of […]

Petitions in the matter of Filing of Tariff Approval of and Determination for FY 2024-25 – EQ

To pass an appropriate order for processing applications of willing consumers in solar net meter scheme for installation of additional capacity by change over from solar net meter scheme

  TANGEDCO/To pass an appropriate order for processing applications of willing consumers in solar net meter scheme for installation of additional capacity by change over from solar net meter scheme For more information please see below link:

Petitions in the matter of Filing of Tariff Approval of and Determination for FY 2024-25 – EQ

APP alleges TANGEDCO demanding heavy discounts from IPPs, seeks power min’s intervention

The APP in its letter to the minister also said that the state-run non-banking firms PFC and REC should be directed to release funds for payment of bills of IPPs, central generating stations and renewable energy projects together. New Delhi: The Association of Power Producers (APP) has written to Union Power Minister R K Singh, […]

Aditya Birla Renewables Raises ₹2,500 Crore Through NCDs – EQ