Tata Power Distribution seeking approval for the Bidding Documents for long term procurement of 225 MW capacity from Wind-Solar Hybrid Projects for meeting its RPO
0
0
Case of The Tata Power Company Ltd – Distribution seeking approval for the Bidding Documents for long term procurement (25 years) of 225 MW capacity from grid connected Wind-Solar Hybrid Power Projects through competitive bidding process for meeting its Renewable Purchase Obligations
For more information please see below link:
Related posts:
- In the matter of: Implementation of Realtime Market (RTM) for Electricity in India – Transmission Corridor Allocation
- Petition seeking relief in time extension granted for commissioning of 50 MW Wind Power Project
- Petition against the termination by NTPC of 300 MW, wind power sale agreement
- TANGEDCO is directed to verify the claim made by the petitioner & settle within 30 days with interest at 12% P.A.