0

Tender Results of SECI’s Gujarat Charanka Solar Park NSM Batch II Phase 4 for 160 MW Grid Connected Solar Projects were declared recently. GIPCL stood L1 & L2 winning 80 MW Projects at a tariff of Rs.4.43 per unit and VGF of Rs.67.99 lakhs/MW for 40MW Project and Rs. 69.75 Lakhs/MW for another 40MW Project. L3 is Orange Renewables winning 40 MW Project at tariff of Rs.4.43 per kWh and VGF of Rs.70.25 Lakhs/MW. L4 is Mahindra winning 40 MW Project at a tariff of Rs.4.43 per kWh and VGF of Rs.77.77 Lakhs/MW