Time Extension in Scheduled Commissioning Date of RE Projects considering disruption due to lockdown due to COVID-19: Clarification
0
0
Time Extension in Scheduled Commissioning Date of Renewable Energy (RE) Projects considering disruption due to lockdown due to COVID-19: Clarification
Further extension beyond 5 months can be granted by implementing agencies in exceptional cases, after due diligence and careful consideration of the specific circumstances of the case, and if allowed in terms of the provisions of the relevant contract.
It is also emphasized that this further extension beyond 5 months will not be granted in a routine manner.
For more information please see below link:
Related posts:
- Covid-19 boost for India’s clean energy sector
- Time-Extension for Renewable Energy (RE) Projects considering disruption due to Iockdown due to COVID-19
- Renewable Energy Industry and the Impact of Novel Coronavirus (Covid-19) – Seeking Relief under these extraordinary circumstances
- Tata Power venture’s 200 microgrids expected to be ready by 2021: Rockefeller Foundation